PROJECT MONITORING & EVALUATION
The Municipality of Alangalang is moving forward with the Rehabilitation of the Multipurpose Building at Real Street, Barangay Sto. Niño, funded under the FY 2024 Local Government Support Fund (LGSF-FALGU) with a budget of ₱50 million. As of June 30, 2026, the project has completed the bidding process, with the Notice of Award issued on May 25, 2026, and the Notice to Proceed set for June 1, 2026. The project is expected to be completed by June 2027.